Water Project Updates

$17.3M capital works project

Proudly funded by the Queensland Government’s Works for Queensland and Local Government Grants and Subsidies and Building Our Regions Programs in association with Tablelands Regional Council.

A new reservoir, pipework and upgrades to intakes were completed in 2022.

Construction of the 13km pipeline to connect Millstream Estate with the Ravenshoe Water Supply Scheme commenced in early June 2023 and should be complete in October 2024.

The construction of the water treatment plant is progressing but there have been some delays. The large pressure filtration tanks have been placed and large sections of stainless steel pipework welded. The portal frame and roof are being built over the filtration and plant room, which will allow work to continue in adverse weather. The treatment plant should be completed in March 2025.

Images © Joseph Estrada, GHD; HEH Civil and TRC.

$10.7M capital works project over two years

The Johnstone River and Peeramon water supply scheme will be connected to the Malanda water supply scheme to accommodate the rapid growth in the area. The project includes design and construction of a 3.19ML reservoir on Glen Allyn Road, and a 4km pipeline from the reservoir to the existing reservoir on Mathers Road.

Fgf Developments Pty Ltd was awarded the contract for the project for $8,326,977.55 including GST. The contract includes additional expenditure of up to $889,057.82 including GST for additional items that may be required during construction, and a contingency allowance of $1,249,046.63 for variations.

The pipeline will be constructed on the road verge on the:

  • east side of Eccles Road
  • north side of Mundey Road
  • east and southeast side of Lake Barrine Road
  • Pioneer Avenue
  • north side of Glen Allyn Road

Some partial road closures may be required. Construction will include trimming of overhanging branches and trenching across driveways. Driveways will be backfilled to maintain access before the end of each day. Fgf’s supervisor will coordinate with residents regarding access.

Site investigations for the pipeline commenced in late May, and main construction in June. The project will take about 10 months to complete. Construction will occur:

  • 7am–6pm Monday–Friday
  • 7am–4pm Saturdays

Connecting pipework is in sight of the reservoir on which the second pour of three has been completed

Calibration of bulk meters and installation of level monitors to meet regulatory requirements. Due for completion in 2025–26.

Service lines (from water mains to meters) are being replaced as part of an ongoing program.

Four-year project to identify and meet future water requirements in Yungaburra due to rapid growth. Improvements include a new water intake (pontoon, pipes, pump and wiring), and water treatment plant and supply upgrades.

Contract T-TRC2023-15 for the replacement of the raw water intake was awarded to Civil Plus Constructions Pty Ltd for $3,248,808.85 including GST. The contract includes additional expenditure of up to $380,868.64 including GST for additional items that may be required during design and construction, and a contingency allowance of $487,321.33 for variations. The project is for the detailed design, construction and replacement of the water intake pontoon on Lake Tinaroo and associated infrastructure.

The project commenced on Monday 9 September and will be completed by June 2025. Construction activities are in full swing with initial pipework and electrical conduits being installed and the submersible pipeline and electrical conduits being welded together. Over the coming weeks the pontoon and pipeline will be floated onto Lake Tinaroo and positioned next to the existing pontoon. Once in place the pipeline and electrical conduits will be sunk and connected to the existing network. The  Yungaburra Water Treatment Plant switchboard will also be replaced.

This project is proudly funded by the Queensland Government’s Local Government Grants Subsidy Program in association with TRC.

Photos © CivilPlus Constructions and TRC.

Develop a delivery program for Atherton and Tolga water supply schemes.

Ongoing capital works projects

Upgrades to pipelines, water meters and pumps across the region as required.

The reservoirs in our region have been assessed and remediation plans are being developed. Options are being investigated for the replacement of reservoirs at Wondecla (High Country Estate) and Mount Garnet.

The Twelfth Avenue reservoir work will include replacement of joint seals, crack injections and concrete repair, and will take about three months to complete.